Thursday, August 18, 2005

Skye Condos III On Track and Progressing as Scheduled

Friends and Owners,

Skye
III is well on track and making good progress. Here are the latest details:

  1. First floor demolition has been completed
  2. Two bathrooms have been sheet rocked (waterproofed)
  3. Demolition is on pace to be completed by the goal date of August 25th.
  4. Bathroom Tile installation will begin late next week
  5. End product renderings will be complete by weeks end (very cool!)
  6. Upgrade of plumbing and electrical will commence mid next week – this is HUGE!

Thanks and stay tuned for updates, details and contact me if you ave any questions.

Chris