Tuesday, October 18, 2005

Fantastic Progress - Cutting Openings for Balconies!

Friends and Owners.

So much behind the scenes work has to happen before you're able to "see" what's going on. Demo,
electrical, plumbing, interior wall removal, etc....FINALLY you can see some of the cool stuff on the EXTERIOR....we re cutting the openings for the balconies including the great news about all the additional balconies that came as a pleasant surprise from our structural engineer and architect!!!

Enjoy a couple pictures and contact me for any questions!

Thanks, Chris

Here are the latest developments at Skye III

Last week’s progress 10/17 – 10/21 :

  1. Got reply from City of Denver regarding structural plans
  2. Completed removal and relocation of all radiators
  3. Continued roughing in of electrical (2 units complete)
  4. Continued installation of plumbing
  5. Set up time to consult with Charlie Wooldridge (artist) on foyers
  6. Received quotes for new mailboxes
  7. Called to schedule Robert Taylor at City of Denver to get final condo map done
  8. Secured floor squeaks
  9. Stone Cutter opened 8 window holes for BALCONIES
  10. Removed all trim in entire building
  11. Secured east gutter
  12. Removed all tile in entryway
  13. Removed all bathroom fans
  14. Demoed outgoing mailbox
  15. Removed door hardware
  16. Removed bathtubs in 3rd floor big units
  17. Removed doors in 3rd floor big units
  18. Interviewed Matt Hemphill as onsite permanent hire